Time is running out to make critical decisions for how to make 14-nm chips expected to hit production in 2015, and capital equipment vendors are falling behind. That was the upshot of a talk by the top R&D executive at Taiwan Semiconductor Manufacturing Co., (TSMC) at Semicon Taiwan.

TSMC believes it needs to move to next-generation lithography and 450-mm wafers to make 14-nm chips cost effectively, but capital equipment makers threaten to miss the foundry's schedule on both fronts. "Every day we become more and more concerned," said Shang-Yi Chiang, senior vice president of R&D of TSMC.

Fabs need throughput of more than 100 wafers per hour. But so far extreme ultraviolet (EUV) lithography offers just five wafers per hour at best. Two alternatives using multiple e-beam direct write approaches get less than one.

Similarly, TSMC "put out our wish list for 450-mm wafers a few months ago, but some in the capital equipment industry felt it was too aggressive so now we don’t know" what the schedule will be, Chiang said to EE Times after his talk. "We may have to do what we did at the 130-nm generation when some capacity was on 200- and some on 300-mm wafers," he said.

TSMC currently plans to bring up a pilot 450-mm wafer line at its Fab 12 in Hsinchu, followed by a production line in Taichung. The larger wafers are needed both to help keep pace with Moore's Law and to lower wafer costs as much as 30 percent.

The 450-nm wafers enable foundries to use fewer fabs, saving significant money on both land and labor costs. To meet expected demand for 32 million eight-inch equivalent wafers, TSMC could hire 20,000 engineers to run 22 plants. If it has to use today's 300-mm wafers the same output would require 29 plants and 27,000 engineers, Chiang estimated.

"450-mm wafers are not a technical issue but an economic issue which is probably more important than technical issue these days," Chiang said.

In lithography, today's 193-nm immersion systems will serve both the 28-nm node TSMC is ramping now and the next-generation 20-nm node. But at 20 nm, fabs will need to use double patterning, essentially running wafers through some exposure